Friday-Saturday working weeks, optional dual Gregorian and Hijri dates on your letters, and notice tracking sized for giga-project subcontract chains, not a single generic project.
Saudi Arabia's construction sector is estimated at $70.33 billion in 2024, projected to reach $91.36 billion by 2029, backed heavily by the Public Investment Fund (PIF) as financier and sponsor of NEOM ($500 billion, headline figure), Red Sea Global ($23.6 billion), and Qiddiya ($9.8 billion). That is the growth story. There is also a more current, more sober one worth knowing if you are pricing risk on a Vision 2030 package right now: PIF's own 2024 annual report disclosed an $8 billion write-down on its giga-project portfolio, The Line at NEOM was suspended in September 2025 and is being redesigned, and the Trojena mountain resort saw roughly $6 billion in contracts terminated after losing its role as host of the 2029 Asian Winter Games to Almaty, Kazakhstan.
Neither story cancels the other out. The pipeline is still enormous by any regional standard. But re-scoping and suspension events are themselves a major source of delay and disruption claims, arguably a bigger source than routine site conditions, and contractors sitting on a re-scoped package need their disruption record just as tight as one sitting on a straightforward site delay.
The Saudi Center for Commercial Arbitration has seen a rapidly growing caseload over recent years as Vision 2030 megaprojects generate more complex infrastructure and joint-venture disputes.
Following a July 2025 Council of Ministers resolution, a draft law from the National Competitiveness Centre aims to align Saudi arbitration practice with international norms, including expedited procedures and remote hearings.
Disruption, not just outright delay, is generally accepted as a valid basis for an extension of time or compensation under Saudi construction contracts, provided it meets the applicable contractual or legal criteria.
Illustrative example, not a real client record.
Employer notice of scope revision received 03 March 2026, redefining the lot boundary and suspending mobilization on the affected zone pending redesign. Sub-Clause 20.1 notice issued 09 March 2026, 6 days after receipt, within the 28-day window. Hijri date on issued letter: 20-09-1447 AH.
Every deadline calculation uses the Kingdom's actual working week, so a notice period counted in working days lands where your contract really means it to.
An optional per-project toggle adds the Hijri date alongside the Gregorian date on letter headers, calculated correctly, for Saudi-facing correspondence.
Giga-project programmes run deep subcontract chains. A single delay or re-scoping event can track the upstream main-contract deadline and the downstream subcontract deadline together.
DraftMyEOT is not a law firm and never claims to be. Every output is a draft, built to be reviewed and signed by your contracts lead or consultant.
No dates, events, or clause numbers appear that you did not supply. Every paragraph shows the evidence reference it was built from.
Each company's workspace is isolated, documents sit in private storage, and consultants see only the project they were invited to.
Send a contract, your delay events, and whatever records exist, tidy or not. A structured draft comes back in 48 hours.